轻质复合夹芯条板
EPS(聚苯乙烯)混凝土节能砌块
当前位置:达权首页 > 安装施工
轻质复合条板安装流程


1、放线、运板就位    在安装墙板的轴线分别上下弹出板厚的双线,根据需要的规格轻松抬到墙边。

2、锯板    根据墙体的规格任意用手提电锯切割。

3、上浆    先在两块板的榫边水泥一道,再将聚合物砂浆任意抹在一块榫边上。

4、安装    将准备安装的条板搬到装拼位置,用铁橇将墙板校正,用力橇靠紧,使聚合物砂浆从接颖挤出至饱满,再用木楔将其临时固定。

5、校正、固定    用2米或2米以上的靠尺检查垂直、平整校正,再用Φ6mm或Φ8mm带肋的钢筋加建筑胶固定。

6、灌浆、补浆    将校正后的墙体墙壁板用聚合物砂浆补满、刮平、上下间隙大的用细石混凝土填补。

7、贴防裂布    在灌缝聚合物及墙体全部定型后,在所有的接缝处用乳胶将玻纤布贴上。

8、安装电线、开关    将要设暗线、开关盒位置放线,再用手提电锯切割开槽,安装完毕后用聚合物砂浆补平。

9、装门框    在安装好的墙上预留门窗洞口,随意用夹板或线条锚固。

10、面饰涂料、墙纸    在装好的墙体上,不需抹灰,直接刮腻子,再刷涂料或贴墙纸。

11、饰面瓷砖、装饰板    在装好的墙体上不需抹灰则可随意粘贴瓷砖或其他木饰面板。

12、电器安装    在装好的室内随意安装灯具、家具、空调、可钉可挂。


 

Installation flow of light weight compound sandwich board


1. Setting the line and carrying the board are in position    Eject double lines of board thickness up and down the axes of installed wall board, easily carry to the side of wall according to the specification needed

2. Sawing board   Using hand-hold electric saw to saw freely according to the specification of wall

3. Sizing:   Sizing cement on tenon side of two boards, then spread polymer mortar on one tenon side casually

4. Installation  Carrying the board prepared to be installed to the installation place, correcting the wall board by gavelock and making it close tightly, and let the polymer mortar squeeze out into full and fixing it with a chock temporarily

5. Correcting, fixing   Using a guiding rule of two meters or longer to check verticality  and leveling correction, then using Φ6mm or Φ8mm reinforcing steel bar with ribs adding with construction sealant to fix.

6. Grouting and filling starch:   Filling and strickling the corrected wall board with polymer mortar, filling the big gap with pea gravel concrete

7. Sticking anti-cracking cloth:   After polymer using for filling the gaps and wall are all shaped, sticking glass-cloth with emulsoid on all seamings

8. Installing electrical wires and switches    Setting lines on the places needing to be set with concealed wire and switch box, then cut a groove by hand-hold electric saw, filling with polymer mortar after installation.

9. Installing doorcase:  Preparing a door and window hole on the installed wall, anchoraging by splint or lines

10. Facing coating and wall papers: Scraping putty directly without plastering on the installed wall, then brushing coating and sticking wall paper.

11. Facing ceramic tile, decorative sheet: Sticking ceramic tiles or other wood facing panels casually without plastering on installed wall

12. Electric apparatus installation:  Install lights, furniture, air-conditioners casually on installed room, nailed or hanged.

 

武汉达权节能板材有限公司 武汉达权进出口有限公司版权所有
地址:湖北省武汉市东湖高新技术开发区  备案号/经营许可号:鄂ICP备07002398号
武汉天地奔腾网络信息技术有限公司(《中华人民共和国增值电信业务经营许可证》:鄂 B2-20040084)提供技术支持